Working days
19
Calendar days
29
Holidays on working days
2

Do it in a spreadsheet

=NETWORKDAYS.INTL(A2,B2,"0000011",Holidays!A2:A20)
  • A2 from date
  • B2 to date
  • Holidays!A2:A20 holiday dates on their own tab

How it works

NETWORKDAYS.INTL counts both ends. The seven-digit code starts on Monday, and 1 means a day off, so "0000011" is a Saturday and Sunday weekend. Keep the holiday dates on their own tab and point the last argument at them.